Amic Pools Build Timeline
Week 1
Pool Excavation, Box and Steel & Concrete Shell
Week 2
Strip Boxing, Site Clean & Run Plumbing
Week 3
Now is the time to organise your permanent pool fence and landscaping quotes
Week 4
Render up ready for coping and apply coping tiles
Week 5 & 6
Electrical and Surrounds can be started
Week 7
Permanent Pool Fence can be erected, once erected pool certifier to check
Week 8
Interior can be applied & Pool Handed Over
Pool Construction Process
Enquiry
Site Visit
Quote
Contract
Box and Steel
Once your pool is excavated, our box and steel crew come in and box your pool, then carefully place steel as per the engineers design. Pre-plumb pipe work is also placed in final location. An independent licensed inspector will make sure that the founding and steel work is in accordance with engineer’s specifications. Once this has been approved, we can go on with the next stage of construction.
Excavation
Building Approval and Engineering
Deposit
Concrete Shell
Once your pool is formed and inspected, the shotcretors come in and shotcrete and shape your swimming pool. This is usually an exciting time for many as they see how their design takes shape! The concrete shell should cure a minimum 21 days.